Ethiopia begins second stage of filling mega-dam, angering Egypt

Egypt described Ethiopia’s launching of the next phase of filling a controversial mega-dam on the Nile River, as “a violation of international laws and norms that regulate projects built on the shared basins of international rivers,” and had expressed its “firm rejection of this unilateral measures.”

The Grand Ethiopian Renaissance Dam, which is set to be Africa’s largest hydroelectric project when completed, is the source of an almost decade-long diplomatic stand-off between Addis Ababa and downstream nations Egypt and Sudan.

Ethiopia says the project is essential to its development, but Cairo and Khartoum fear it could restrict their citizens’ water access.

Both countries have been pushing Addis Ababa to ink a binding deal over the filling and operation of the dam, and have been urging the UN Security Council to take the matter up in recent weeks.

Thursday’s meeting was requested by Tunisia on Egypt and Sudan’s behalf, a diplomatic source told AFP.

But France’s ambassador to the UN said last week that the council itself can do little apart from bringing the sides together.

Egypt’s Foreign Minister Sameh Shoukry said in one note to the UN that negotiations are at an impasse, and accused Ethiopia of adopting “a policy of intransigence that undermined our collective endeavors to reach an agreement.”

Addis Ababa had previously announced it would proceed to the second stage of filling in July, with or without a deal.

The Nile — which at some 3,700 miles (6,000 kilometres) is one of the longest rivers in the world — is an essential source of water and electricity for dozens of countries in East Africa.

Egypt, which depends on the Nile for about 97 per cent of its irrigation and drinking water, sees the dam as an existential threat.

Sudan hopes the project will regulate annual flooding but fears its dams would be harmed without agreement on the Ethiopian operation.

The 145-metre (475-foot) mega-dam, on which construction began in 2011, has a capacity of 74 billion cubic metres.

Filling began last year, with Ethiopia announcing in July 2020 it had hit its target of 4.9 billion cubic metres — enough to test the dam’s first two turbines, an important milestone on the way towards actually producing energy.

The goal is to impound an additional 13.5 billion cubic metres this year.

Egypt and Sudan wanted a trilateral agreement on the dam’s operations to be reached before any filling began.

But Ethiopia says it is a natural part of the construction, and is thus impossible to postpone.

Last year Sudan said the process caused water shortages, including in the capital Khartoum, a claim Ethiopia disputed.

Sudan’s water minister Yasser Abbas warned in April that if Ethiopia went ahead with the second stage filling, Sudan “would file lawsuits against the Italian company constructing the dam and the Ethiopian government”.

    Source: